Decision Maker: Cabinet
Decision status: Recommendations approved
Is Key decision?: Yes
Is subject to call in?: No
Decisions:
Councillor
Lucy Smith, Deputy Leader and Cabinet Member for Children and Young
People, presented the report which requested Cabinet approval of
the project sum for works in relation to the Pupil Referral Unit,
following conclusion of the tender exercise, and specifically in
relation to the PRU’s Whitefield Centre building. These are
phase 2 of works following the relocation of the main PRU building
from Spring Lane to the New Kershaw Centre.
A member
requested that there is ongoing consultation with residents in the
local area throughout the process and highlighted a known query in
relation to the site entrance which is currently being looked
into.
Decision:
Cabinet:
- Approved
the project sum value, the extent of works and programme detailed
within part B of this report.
- Delegate
authority to the Executive Director of Education in consultation
with the Director of Law and Governance to negotiate and execute
the building contract.
Reasons for
recommendation(s):
- Approval of
the works is required in order for the Whitefield Centre project to
progress to manufacture and construction phase. Key considerations
within this document have informed both the scope and the
methodology for carrying out the works as proposed.
Alternative
options considered and rejected:
- Delay
instructing the contract: This would delay overall Whitefield
Centre completion date by two months as Cabinet approval cannot be
sourced in the August cycle. This would prevent the school from
receiving the additional intake of pupils in and they would have to
be housed in alternative provision outside the Borough of Bury.
This would also push the works into the winter months, potentially
extending the duration on site and associated costs of
construction.
- Seek an
alternative solution for the contract: The Council have considered
alternative options to deliver the additional accommodation within
the timescales provided. This included use of other Council owned
property, and the use of modular accommodation on the existing
site, partial reconfiguration only. No other Council owned property
could meet the needs of the school within the available timescale.
Partial reconfiguration would not provide the classroom
accommodation the school requires and there was insufficient space
within the school to site modular accommodation or extend. A split
site was also discounted as the school would not have the staffing
and safeguarding arrangement available to accommodate this. None of
alternative options explored where able to deliver the additional
accommodation with the available timescales.
Publication date: 30/07/2024
Date of decision: 16/07/2024
Decided at meeting: 16/07/2024 - Cabinet
Accompanying Documents: