Decision Maker: Cabinet
Decision status: Recommendations approved
Is Key decision?: Yes
Is subject to call in?: No
Decisions:
Councillor
Eamonn O’Brien, Leader and Cabinet Member for Strategic
Growth, presented the report which advised Cabinet of the Enabling
Works and Main Works packages, that in line with the Bury Market
& Flexi Hall project programme, will now need to be instructed
through the Enabling Works and Main Works
Contract.
In response
to a Member’s query regarding the Levelling-up fund members
were assured that no issues are expected to arise due to national
political changes. Members were informed that national changes will
provide a kick-start to other projects such as the Mill Gate. The
Leader assured members that it is no coincidence that two of the
levelling up schemes sit in areas with the highest level of
deprivation and all will be done to ensure these schemes are
delivered.
A member gave
praise to the equality duties being considered and raised a point
from residents with health conditions and proximity to bathroom
facilities. The Cabinet was informed
that the Flexi-Hall should alleviate the distance to a bathroom in
future and sign posting to the nearest bathroom will be considered
in the surrounding infrastructure. Members recognised that the
Indoor market is closed and is a place previously used to access
these facilities. Robert Summerfield, Assistant Director advised
changing places and toilet facilities will be
checked.
Decision:
Cabinet:
- Approved
the delivery of Enabling Works and Main Works packages to be
undertaken by Vinci Construction UK Ltd.
- Agreed the
interim tender report recommendation that Vinci Construction UK Ltd
undertake the Enabling Works and Main Works packages at the
provisional contract sum set out in Part B of this report, and
delegate final acceptance of a final contract sum up to a
provisional maximum of £25,088,003.87 to the Director of Law
and Democratic Services in consultation with the Executive Director
of Place and Director of Finance and the Council Leader and Cabinet
Member for Strategic Growth.
- Agreed to
delegate finalisation and sealing of the Enabling Works and Main
Works Contract including any clarifications to the Director of Law
and Democratic Services in consultation with the Executive Director
of Place and the Council Leader and Cabinet Member for Strategic
Growth.
Reasons for
recommendation(s):
- Approval of
the Enabling Works package is required for the Bury Market &
Flexi Hall project to deliver various preparatory works on site.
These works are required to be completed in advance, to ensure the
Main Works construction phase can start on time in line with the
agreed project programme, associated scheme cash flow and DLUHC
Levelling Up grant spend deadline. Approval also extends to the
Main Works package for the Bury Market & Flexi Hall project to
progress to a construction phase without delay and to avoid
jeopardising development delivery and grant funding expenditure
obligations. Key considerations within this document have informed
the Enabling Works and Main Works contract sum, the scope and
methodology for carrying out the associated Enabling Works and Main
Works packages and their phasing in line with the agreed project
programme and grant funding agreement.
Alternative options considered and
rejected:
- Delay
instructing the Enabling Works and Main Works Contract: Delaying
the starting dates for the Enabling Works and Main Works packages
would further delay both the full defrayment of the Levelling Up
grant and the overall delivery of the Bury Market & Flexi Hall
scheme. In turn this would jeopardise the Council’s
obligations set out in the MoU as agreed with DLUHC and put at risk
the Levelling Up grant monies.
- Any further
delay incurred would also erode confidence in the Council’s
ability to deliver a key strategic priority for Bury which is also
critical to supporting the delivery of a number of major, corporate
strategies and Team Bury initiatives including the Council’s
‘Let’s Do It’ Vision and Strategy, Bury Town
Centre Regeneration Masterplan, Bury Town Centre Evening and Night
Time Economy Strategy, Bury Economic Strategy, Bury Interchange
redevelopment and the Millgate Strategic Regeneration Framework,
amongst others.
- Further
delays to starting the Enabling Works and Main Works would also
incur significant additional costs to the Council, including build
cost inflation due to further scheme prolongation, and additional
professional fees, including the Council’s external
professional team. Delays may also incur potential additional
contractor preliminary costs that might feasibly be requested under
the terms of the existing PCSA contract (the prelim rate currently
stands at circa £8.1k per week).
- On top of
these costs, the Council would also incur additional, consequential
costs in respect to extra rents and service charges that it will
have to pay regarding the temporary accommodation that houses the
Bury Market service (12 Princess Parade). The Council would also
have to pay additional business rates charges in respect to those
properties (Nos 2 – 10 Princess Parade) which it has already
acquired in readiness for demolition and on whose cleared site the
footprint of the new Flexi Hall will be constructed.
- Furthermore,
delays to instructing the Enabling Works and Main Works Contract
could mean that subcontractor prices expire with the resulting risk
that the overall tender price increases in line with market
fluctuations at the time. In this regard, the tendered price is
fixed until the anticipated date of a Cabinet approval decision
(July 2024) but any delays beyond this date will risk the tender
price increasing because Vinci’s supply chain cannot fix
prices for a longer period.
Publication date: 30/07/2024
Date of decision: 16/07/2024
Decided at meeting: 16/07/2024 - Cabinet
Accompanying Documents: