To accept the application and to instruct
Legal Services to make the appropriate orders to secure the
diversion of a non-definitive footpath at Warth Fold, Bury. The
path (shown in the attached plan PRW/ND/WARTH/BURY/1) is located in
an area to be used for the construction of flood defences. It is
proposed that a bund will be created across the line of the path,
making access along the route very difficult with a gradient that
would create an obstruction to some potential users of the path.
The diversion removes the need to traverse the gradient.
The land for the existing and proposed diverted paths is owned by
St Modwen Development Ltd. and they have agreed with the
Environment Agency that works can take place on their land and that
the footpath can be diverted. Planning permission has been sought
for the flood defences (Planning No.65171) and a diversion will be
required to allow the development to take place, subject to
planning permission being granted. The existing path (A-B on the
plan) is unsurfaced and runs beside a high concrete fence, at the
base of the Metrolink embankment and is 250m in length. The
diversion (A-D-C-B) would maintain access to the area via a sloped
and more accessible route which passes through an open landscaped
area and is 330m in length. The bridge across the River Irwell
carries the Metrolink and has a pedestrian walkway beneath that
offers access to and from the existing and diversion routes. The
diverted route will be added to the Authority’s Public Rights
of Way Definitive Map and Statement.