Decision details

Approval to spend £220,356.55 from the allocated and approved Operations Capital Programme 2020/21 to contribute to phase 1 of Bury’s sustainable tennis development in partnership with the Lawn Tennis Association (LTA)

Decision Maker: Executive Director of Operations

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Approval to spend £220,356.55 from the allocated and approved Operations Capital Programme 2020/21 to contribute to phase 1 of Bury’s sustainable tennis development in partnership with the Lawn Tennis Association (LTA)

Also approval for the award of contract for the tennis court redevelopment and access control system for phase 1 at Hamilton Road Park, Openshaw Park, Nuttall Park, Bolton Road Park, Manchester Road Park and Whitehead Park for completion in 2020/21 as well as the remaining three elevations of fencing at St Mary’s Park.

Publication date: 13/10/2020

Date of decision: 16/09/2020