Decision details

Watling St, Tottington – Temporary Road Closure

Decision Maker: Executive Director of Operations

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Temporary closure under Section 14(1) of the Road Traffic Regulation Act 1984, of Watling St, Tottington between nos 88 & 94 from Tuesday 12/01/21 for a period of 3 months to facilitate electrical connection works (anticipated duration of works 2 weeks). The diversion route is via Tottington Rd, Lee Gate, Bradshaw Rd & Turton Rd, Bolton & vice versa.

Publication date: 13/12/2020

Date of decision: 07/12/2020

Accompanying Documents: