Decision details

Prestwich Village Regeneration Project: Demolition of the Longfield Shopping Centre – Increase in Demolition Costs

Decision Maker: Executive Director of Operations

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

On 3rd December 2025, Cabinet approved the commitment of £3,250,000 to enable Muse Places (delivered on behalf of the Prestwich Regeneration LLP – the Joint Venture) to complete design, planning and demolition work packages required to achieve three agreed milestones as set out by the Greater Manchester Combined Authority (GMCA). This was to secure GMCA funding to support delivery of the next phase of the Prestwich Village Regeneration Project.

Publication date: 07/10/2026

Date of decision: 14/08/2026

Accompanying Documents: