420 CORPORATE PLAN PROGRESS REPORT - QUARTER 1 2013-2014 PDF 85 KB
A report from the Leader of the Council is attached.
Additional documents:
Minutes:
The Leader of the Council submitted a report outlining the progress made on the Corporate Plan during quarter one (2013-2014) for the corporate performance indicators and projects within the Bury Council Corporate Plan.
During discussion of this item an undertaking was given to provide Members with a detailed definition in respect of the indicator relating to the supply of housing sites.
It was agreed:
That Officers be thanked for the good performance highlighted in the report and a further update be submitted at the end of Quarter 2, 2013/14.
390 Corporate Plan Progress Report - Quarter 1 2013-2014 PDF 85 KB
Additional documents:
Minutes:
The Leader of the Council submitted a report outlining the progress made on the Corporate Plan during quarter one (2013-2014) for the corporate performance indicators and projects within the Bury Council Corporate Plan.
Delegated decision:
That the report be noted.
Reason for decision:
The report provides a clear indication of the overall performance made against the Corporate Plan.
Other option considered and rejected:
To reject the recommendation.