188 Bury Market & Flexi Hall Levelling Up scheme – enabling and main works contract - Part A PDF 461 KB
Report of the Leader and Cabinet Member for
Strategic Growth is attached
Additional documents:
Minutes:
Councillor
Eamonn O’Brien, Leader and Cabinet Member for Strategic
Growth, presented the report which advised Cabinet of the Enabling
Works and Main Works packages, that in line with the Bury Market
& Flexi Hall project programme, will now need to be instructed
through the Enabling Works and Main Works
Contract.
In response
to a Member’s query regarding the Levelling-up fund members
were assured that no issues are expected to arise due to national
political changes. Members were informed that national changes will
provide a kick-start to other projects such as the Mill Gate. The
Leader assured members that it is no coincidence that two of the
levelling up schemes sit in areas with the highest level of
deprivation and all will be done to ensure these schemes are
delivered.
A member gave
praise to the equality duties being considered and raised a point
from residents with health conditions and proximity to bathroom
facilities. The Cabinet was informed
that the Flexi-Hall should alleviate the distance to a bathroom in
future and sign posting to the nearest bathroom will be considered
in the surrounding infrastructure. Members recognised that the
Indoor market is closed and is a place previously used to access
these facilities. Robert Summerfield, Assistant Director advised
changing places and toilet facilities will be
checked.
Decision:
Cabinet:
- Approved
the delivery of Enabling Works and Main Works packages to be
undertaken by Vinci Construction UK Ltd.
- Agreed the
interim tender report recommendation that Vinci Construction UK Ltd
undertake the Enabling Works and Main Works packages at the
provisional contract sum set out in Part B of this report, and
delegate final acceptance of a final contract sum up to a
provisional maximum of £25,088,003.87 to the Director of Law
and Democratic Services in consultation with the Executive Director
of Place and Director of Finance and the Council Leader and Cabinet
Member for Strategic Growth.
- Agreed to
delegate finalisation and sealing of the Enabling Works and Main
Works Contract including any clarifications to the Director of Law
and Democratic Services in consultation with the Executive Director
of Place and the Council Leader and Cabinet Member for Strategic
Growth.
Reasons for
recommendation(s):
- Approval of
the Enabling Works package is required for the Bury Market &
Flexi Hall project to deliver various preparatory works on site.
These works are required to be completed in advance, to ensure the
Main Works construction phase can start on time in line with the
agreed project programme, associated scheme cash flow and DLUHC
Levelling Up grant spend deadline. Approval also extends to the
Main Works package for the Bury Market & Flexi Hall project to
progress to a construction phase without delay and to avoid
jeopardising development delivery and grant funding expenditure
obligations. Key considerations within this document have informed
the Enabling Works and Main Works contract sum, the scope and
methodology for carrying out the associated Enabling Works and Main
Works packages and their phasing in line with the agreed project
programme and grant funding agreement.
Alternative options considered and rejected:
...
view the full minutes text for item 188
Bury Market & Flexi Hall Levelling Up scheme – enabling and main works contract - Part B
Report of the Leader and Cabinet Member for
Strategic Growth is attached.
Additional documents:
- Restricted enclosure 6
- Restricted enclosure 7
- Restricted enclosure 8
- Restricted enclosure 9
Minutes:
Councillor Eamonn
O’Brien, Leader and Cabinet Member for Strategic Growth
presented the Part B report regarding Bury Market and Flexi Hall.
The report set out the full financial details.
Decision:
Cabinet:
- Approved the delivery
of Enabling Works and Main Works packages to be undertaken by Vinci
Construction UK Ltd.
- Accepted the interim
tender report recommendation that Vinci Construction UK Ltd
undertake the Enabling Works and Main Works packages at the
provisional contract sum set out in Part B of this report, and
delegate final acceptance of a final contract sum up to a
provisional maximum of £25,088,003.87 to the Director of Law
and Democratic Services in consultation with the Executive Director
of Place and Executive Director Finance and the Council Leader and
Cabinet Member for Strategic Growth.
- Delegated
finalisation and sealing of the Enabling Works and Main Works
Contract including any clarifications to the Director of Law and
Democratic Services in consultation with the Executive Director of
Place and the Council Leader and Cabinet Member for Strategic
Growth.
Reasons for the decision:
Other
options considered and rejected: