The Acceptance of the Lowest Tender for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3)

Meeting: 16/07/2024 - Cabinet (Item 202)

The Acceptance of the Lowest Tender for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3) - Part B

Report of the Cabinet Member for Environment, Climate Change and Operations attached.

 

Minutes:

Councillor Alan Quinn, Cabinet Member for Environment and Climate Change presented the Part B report regarding the replacement of Existing Street Lighting Lanterns with LED Lanterns. The report set out the full financial details.

 

Decision:

Cabinet:

  • Accepted the lowest tender submitted by E.ON Energy Solutions Ltd.

 

Reasons for the decision:

 

  • As set out for Part A.

 

Other options considered and rejected:

 

  • As set out for Part A.

 


Meeting: 16/07/2024 - Cabinet (Item 194)

194 The Acceptance of the Lowest Tender for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3) - Part A pdf icon PDF 240 KB

Report of the Cabinet Member for Environment, Climate Change and Operations attached.

Minutes:

Councillor Alan Quinn, Cabinet Member for Environment, Climate Change and Operations, presented the report which requested Cabinet approval to accept the lowest tender submitted for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3) by E.ON Energy Solutions Ltd.

 

In response to a members query in relation to the increase or decrease in brightness of street lights member were informed that this is possible, however, decisions must always be based on public safety over hobbies or other matters.

 

Decision:

Cabinet:

 

  • Approved the award of a contract to E.ON Energy Solutions Ltd in the sum set out in Part B of this Report.
  • Agreed to delegate authority to the Executive Director of Operations in consultation with the Director of Law and Governance to negotiate and execute the contract

 

Reasons for recommendation(s):

 

  • A mini competition was undertaken, via The Chest, in accordance with the terms of the GMCA Street Lighting Electrical Connections Framework. The Framework includes the provision of electrical connections to street lights (and other associated highway furniture) such as new connections, disconnections and transfers. The Framework is a compliant procurement process under the Public Contracts Regulations 2015.
  • Four eligible companies were invited to participate and E.ON submitted the most competitive price

 

Alternative options considered and rejected:

 

  • The inhouse were considered. However, they do not have the capacity to carry out this work on top of their day-to-day commitments.
  • There is the option to do nothing. However, this will not replace old, and expensive to operate/maintain, street lighting lanterns and achieve the energy savings required.