Northern Gateway, Western Access scheme

Meeting: 14/10/2026 - Cabinet (Item 79)

79 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding. pdf icon PDF 299 KB

Report of the Leader is attached.

Minutes:

Councillor O’Brien introduced the report seeking Cabinet approval of the Bentley Project Management sum of £423k, to cover the remaining Stage 2B period, and subsequent Stage 3 works, concluding the scheme’s Pre-Construction Period and highlighting that this is an important development site for both Bury and wider area.

 

Councillor Rydeheard queried the provisional maximum and whether any allowances have been made of if this would be exceeded and whether there is any room for manoeuvre.

 

Councillor O’Brien confirmed that we are not forecasting to exceed it.  If we do go over for any reason, would need to return to cabinet to make an additional decision.

 

Councillor Vernon queried paragraph 16 around Councils commercial risk and the included break clause and mechanisms.  If costs do spiral out of control are the developers liable as much as Bury Council. 

 

Councillor O’Brien advised that at this stage we can have a lot more certainty around the budget, however projects do get delayed and costs increase.  We are attempting to pre-empt this and can be reasonably assured that this a is a robust estimate and provide assurance that there are checks and balances in the approach. 

 

Decision(s)

Cabinet:

a.   Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up to a provisional maximum of £3,129,915, covering the finalisation of the Detailed Design/ Full Business Case stage work packages (Stage 3), to the Director of Law and Democratic Services in consultation with the Executive Director of Place and Director of Finance and the Leader.

b.   Approved the Bentley Project Management (UK) Limited contract sum of £423,000 covering the remaining Pre-Construction Stages of the scheme (finalisation of Stage 2b Outline Business Case/ Preliminary Design stage, and Stage 3 Full Business Case/ Detailed Design stage). 

c.    Accepted the remaining £8.5 million of Investment Zone capital grant funding allocated to the Western Access scheme, for inclusion in the Council’s Capital Programme.

 

Reasons for decision(s)

·         The Western Access scheme (Pilsworth Road Corridor Improvements) is a cross-boundary scheme with Rochdale Council, and will provide the necessary off-site, highway and transportation infrastructure required to access the early development phases of the Northern Gateway Investment Zone (IZ) site (JPA 1.1 allocation). The construction of the Western Access scheme will create the potential capacity to unlock up to 600,000 sqm of employment generating uses and support the creation of high quality, employment floor space, including space within the advanced manufacturing and foundational sectors. 

·         The completion of on-going Stage 2b activities to finalise the Outline Business Case (OBC) for the Western Access scheme will result in a preferred option for the scheme being identified and associated Preliminary Designs and an updated scheme budget estimate being prepared. Importantly, the OBC will also provide the robust strategic, economic, commercial and financial cases for the scheme. This in turn will provide the firm foundation for the development of the subsequent Stage 3 Full Business Case (FBC), which will confirm detailed designs and costings. 

·         Investment Zone (IZ) year one revenue grant funding was allocated  ...  view the full minutes text for item 79