Issue - meetings

Combined PRU & AP facility in Radcliffe

Meeting: 04/11/2026 - Cabinet (Item 7.)

7. Call-In - New Ash Grove Additional Provision Academy pdf icon PDF 30 KB

Additional documents:


Meeting: 03/11/2026 - Overview and Scrutiny Committee (Item 5.)

5. Call-In - New Ash Grove Additional Provision Academy pdf icon PDF 210 KB

Following the receipt of a Notice of Call-in within the required deadline, from Councillor J Sheppard and Councillor C Birchmore calling in the decision of the Cabinet at the meeting held on the 14th October 2026 a meeting of the Committee has been convened in order to consider the matter in accordance with the reasons set out on the Notice of Call-In.

 

In considering the matter, the options available to the Scrutiny Committee are as follows:

 

  1. The Scrutiny Committee decides not to offer any comments on the Notice. In this situation the decision of the Cabinet will stand.

 

  1. The Scrutiny Committee decides to offer comments or

objections, which will be referred back to the Cabinet  

 

  1. The Scrutiny Committee may refer the Notice, without comment, to the Council. The matter will then be considered by the Council (a standard item appears on all Council summons to consider referrals from Scrutiny Committees). Any comments or objections from Council will be referred back to the Cabinet at the earliest opportunity, in accordance with the Council Constitution.

 

The Cabinet will be required to consider any objections and comments but will not be bound by them unless "it is contrary to the Policy Framework or contrary to or not wholly consistent with the Budget"

 

Within the agenda pack included for this call in item are the below;

 

·       Original Cabinet Paperwork and Appendix

·       Decision Minute From Cabinet

·       Call in Request

·       Scrutiny Report Addressing Call in Concerns

·       Appendix with descriptions of contents to support the scrutiny report

 

Additional documents:


Meeting: 14/10/2026 - Cabinet (Item 83)

83 New Ash Grove Additional Provision Academy pdf icon PDF 210 KB

Report of the Cabinet Member for Children and Young People is attached.

Additional documents:

Minutes:

Councillor Walmsley introduced the report seeking to progress the delivery of a new permanent facility for the Ash Grove Alternative Provision (AP) Academy on the proposed Milton Road site in Radcliffe. The proposal represents a significant investment in the borough's education infrastructure and forms a key element of the Council's commitment to improving outcomes for some of Bury's most vulnerable children and young people.

 

The Council has a statutory responsibility to ensure that appropriate educational provision is available for children who are unable to access mainstream education. In December 2024, the Council entered into a legal agreement with Oak Learning Partnership (OLP) to provide a permanent, single-site location for Ash Grove Alternative Provision Academy by September 2028. The proposed development will replace the current temporary arrangements across multiple sites, creating a modern, purpose-built facility capable of accommodating up to 136 pupils in an inclusive, supportive, and adaptable learning environment.

 

The development will support the delivery of the Council's Alternative Provision Strategy; address identified gaps in local educational provision and ensure compliance with statutory and contractual obligations. Importantly, it will provide a long-term, sustainable solution that improves educational opportunities, strengthens support for vulnerable learners, and reduces the Council's reliance on temporary accommodation and external provision arrangements.

 

The Council has a statutory duty under Section 19 of the Education Act 1996 to provide suitable education for children who cannot attend mainstream school due to exclusion, illness, or other reasons. Alternative Provision (AP) is therefore not discretionary; it is a legal requirement.  Bury currently lacks a permanent site for its main AP. Following relocation from the former Spring Lane site, provision operates from temporary accommodation across two locations, creating operational inefficiencies, and limiting the development of a coherent local Alternative Provision offer for our children.

 

Councillor Birchmore queried why the cost per pupil is so much higher than star academy and whether we know how many permanent exclusions there were last year?

 

Councillor Walmsley confirmed that  alternative provision costs more per pupil than general population schooling.  She also confirmed there were 66 permanent exclusions last year. 

 

Ben Dunne, Director, Education & Skills added that permanent exclusions across Bury are far too high compared to our Greater Manchester neighbours. The vast majority of our suspensions and permanent exclusions sit in secondary schools.  This is also a national issue.  An alternative provision academy that provides a genuine inclusion hub, outreach support, short term intervention places and provides a centre for excellence all hinge around a provision setting that can focus on those things.  This is an opportunity to intervene earlier and support schools earlier so they don’t find themselves in a situation where they have to permanently exclude children. 

 

As we haven’t had these options in Bury before, we have had to rely on expensive independent specialist placements, out of borough provision, high transport costs, crisis interventions, and high numbers of youngsters going  into youth justice.

 

Alternative provision can be a turning point for young people.  Perception that the new alternative provision is for a new  ...  view the full minutes text for item 83