Agenda and minutes

Urgent meeting, Cabinet - Friday, 27th March, 2026 2.00 pm

Please let us know if you are planning to attend and have any access requirements or other needs which we need to take account of.

Venue: Council Chamber - Town Hall. View directions

Contact: Philippa Braithwaite  Democratic Services

Items
No. Item

CA.156

Apologies for Absence

Minutes:

Apologies were received from Councillors Morris, Quinn, Tariq and Walmsley

CA.157

Declarations of Interest

Members of Cabinet are asked to consider whether they have an interest in any of the matters of the Agenda and, if so, to formally declare that interest.

Minutes:

There were no declarations of interest.

CA.158

Prestwich Village Regeneration Project: Phases 1B & 2 Appointment of Pre-Construction Services Agreement Contractor Part A pdf icon PDF 521 KB

Minutes:

The Leader and Cabinet Member for Strategic Growth presented a report regarding the Prestwich Village Regeneration Project which will deliver a comprehensive redevelopment of the Prestwich Village site including the Longfield Centre.

 

Decision:

Cabinet:

1.    Accepted the tender process that was undertaken via a Public Contracts Regulations 2015 (PCR 2015) was a compliant process and approved the appointment of VINCI Construction UK Limited (company number 02295904) to supply PCSA provision for Phases 1B and 2 for a fee of £0, subject to the agreement of the contract terms and conditions and final scope of services.

2.    Approved a delegation of authority to the Executive Director of Place in consultation with the Director of Law and Governance to finalise contractual arrangements. To note that the Director of Law and Governance will execute the contract in accordance with the Constitution, noting that the contract will need to be executed as a Deed under seal to ensure it is binding as there is no consideration/fee.

3.    Approved the Prestwich Regeneration LLP (the JV) to enter into negotiations with VINCI Construction UK Limited (company number 02295904) for the delivery of the main contract works through an open-book collaborative tender process.

 

 

Reasons for the decision:

Approval of the PCSA will enable the full completion of one of the three GMCA milestones (“The JV to have selected a main contractor, agreeing the relevant PCSA”) to be met before the end March 2026. This will allow the Council to secure funding to deliver the next phase of the Prestwich Village Regeneration Project.

 

Delegating authority to the Executive Director of Place in consultation with the Director of Law and Governance to finalise contractual arrangements will enable the contract to be executed without delay and within the required timeframes.

 

A PCSA utilises a two-stage procurement route where the same contractor who has been appointed to develop the design and price is usually (subject to an open-book negotiation) the appointed contractor to undertake the main works. Reasons include buildability and programme certainty, better cost certainty and risk management, faster mobilisation, single point continuity and is better value for money

 

Alternative options considered and rejected

No alternative option of selecting the PCSA contractor has been considered as the tender process was via a framework ensuring procurement was competitive and conducted in a fair, transparent and open manner.

 

Delegation to key senior officers ensures expedient appointment of the PCSA contractor to meet GMCA timescales. As there is currently no clear alternative route to external funding for the project, other than that which is on offer from the GMCA, meeting their timescales is essential to the success of the project to secure full project delivery.

 

A new and separate tender process was considered to appoint the main works contractor, but this would likely result in less buildability due to not having had the input during design, higher risk of bids including a larger risk allowance, longer programme and weaker cost certainty. Pre-contract negotiations will also be significant that will add time onto the  ...  view the full minutes text for item CA.158

CA.159

Exclusion of Press and Public

To consider passing the appropriate resolution under Section 100 (A)(4), Schedule 12(A) of the Local Government Act 1972, that the press and public be excluded from the meeting for the reason that the following business involves the disclosure of exempt information as detailed against the item.

Minutes:

Decision:

That the press and public be excluded from the meeting under Section 100 (A)(4), Schedule 12(A) of the Local Government Act 1972, for the reason that the following business involves the disclosure of exempt information as detailed against the item.

CA.160

Prestwich Village Regeneration Project: Phase 1B & 2 Appointment of Demolition Contractor Part B

Additional documents:

Minutes:

The Leader and Cabinet Member for Strategic Growth presented the Part B report regarding the Prestwich Village Regeneration Project which included full financial details.

 

Decision:

Cabinet:

1.    Accepted the tender process that was undertaken via a Public Contracts Regulations 2015 (PCR 2015) was a compliant process and approved the appointment of VINCI Construction UK Limited (company number 02295904) to supply PCSA provision for Phases 1B and 2 for a fee of £0, subject to the agreement of the contract terms and conditions and final scope of services.

2.    Approved a delegation of authority to the Executive Director of Place in consultation with the Director of Law and Governance to finalise contractual arrangements. To note that the Director of Law and Governance will execute the contract in accordance with the Constitution, noting that the contract will need to be executed as a Deed under seal to ensure it is binding as there is no consideration/fee.

3.    Approved the Prestwich Regeneration LLP (the JV) to enter into negotiations with VINCI Construction UK Limited (company number 02295904) for the delivery of the main contract works through an open-book collaborative tender process.

 

Reasons for the decision:

As for the Part A report.

 

Alternative options considered and rejected

As for the Part A report.