Agenda and draft minutes

Audit Committee - Monday, 8th December, 2025 7.00 pm

Please let us know if you are planning to attend and have any access requirements or other needs which we need to take account of.

Venue: Council Chamber - Town Hall. View directions

Contact: Andrea Tomlinson  Democratic Services

Items
No. Item

AU.106

APOLOGIES FOR ABSENCE

Minutes:

There were no apologies for absence.

 

AU.107

DECLARATIONS OF INTEREST

Members of the Audit Committee are asked to consider whether they have an interest in any of the matters on the agenda and, if so, to formally declare that interest.

 

Minutes:

There were no declarations of interest made at the meeting.

 

AU.108

MINUTES OF THE LAST MEETING pdf icon PDF 279 KB

The Minutes of the last meeting of the Audit Committee held on

Minutes:

It was agreed:

 

That the Minutes of the last meeting held on 20 October be approved subject to the following amendments: -

 

Minute AU.98 Council Improvement Plan,

In reference to Financial Resilience, the S.151 Officer reported that the matter would be considered at the December Meeting and not the November meeting as stated in the report.

 

Minute AU.99 2024/2025 Draft Accounts

Councillor Moss referred to the Narrative of both the Annual Governance Statement section of the Draft Accounts and the Annual Governance Statement which included the Head of Audit Opinion of Limited Assurance and stated that as there were a large number of limited assurance audits with a high number of recommendations attached and stated that the narrative in both the  AGS and Draft Accounts statement should include this more prominently to reflect the seriousness.

 

The S.151 Officer and the Monitoring Officer had agreed that this would be done.

 

Mr Thomas, Independent Member referred to external providers in relation to the accounts process such as the GMPF and asked how their work was monitored and challenged if needed and how they could be held to account.

 

 

AU.101 External Audit Progress Report.

Mr Webster referred the 24/25 Financial Statements Audit the 2024/2025 being disclaimed and asked whether there was a plan or timetable in place in relation to the 24/25 accounts.

 

AU.109

MATTERS ARISING

Minutes:

There were no matters arising.

AU.110

EXTERNAL AUDIT ANNUAL REPORT pdf icon PDF 542 KB

Report from Bury’s External Auditors is attached

Minutes:

Karen Murray and Osama Rathore presented the Draft Auditor’s Annual report summarising the work Forvis Mazars have undertaken as the auditor for Bury Council (‘the Council’) for the year ended 31 March 2025.

 

It was reported that the Council did not meet the statutory publication date of 30 June 2025 for its unaudited financial statements for the year ending 31 March 2025. The draft statements were not published until 15 October 2025.

 

Forvis Mazars have not commenced work on the financial statements and it was explained that they expect to complete the work and issue their opinion on the financial statements in February 2026. Forvis Mazars expect to issue a disclaimed audit report.

 

It was also reported that that the external auditors had considered there was a significant risk the weaknesses they had previously identified had not been addressed. The risks had been reported, and the work they planned to do to address them, to the Council. However, they have been unable to complete the work planned as the Council had not yet provided evidence to support the improvements in all areas.

 

A more thorough report will be presented to the Audit Committee at its next meeting in February 2026.

 

Those present were given the opportunity to ask questions and the following points were raised:

 

  • Councillor Hook referred to the statement that council evidence had not been provided and asked whether this was more to do with timing and capacity.

 

The external auditor explained that it was both, the council could have provided some information in certain areas as the auditors had been requesting it since June. There had been a lack of engagement.

 

The S.151 Officer explained that there was some budget work that needed completing before sharing and capacity had been an issue.

 

  • Councillor Moss referred to VFM comments last year in relation to Childrens Services and asked about progress made.

 

The S.151 Officer explained that this was in relation to project safety valve. There had not been as much progress made in relation to this as the Council would have liked but it was a national issue  and the council were awaiting further information from the DfE.

 

The External Auditor explained that the Council had been slow at providing a response  and they had hoped that the changes which had been implemented would have helped the S.151 Officer and his team to provide  the information requested.

 

The S.151 Officer explained that governance arrangements had seen the implementation of six assurance groups that meet every Month in relation to the weaknesses identified. The progress made is reported to the Audit Committee at each meeting.

 

  • Mr Webster stated that on page 15 of the External Auditor’s report it referred to the issue of the statutory recommendation in December 2025, Mr Webster asked if this should have read 2024.

 

  • Mr Webster asked if any questions had been received during the public inspection period and asked if there was a timetable of work to February in place.

 

The External Auditor reported  ...  view the full minutes text for item AU.110

AU.111

RISK REGISTER pdf icon PDF 533 KB

Report from the Section 151 Officer attached

Additional documents:

Minutes:

The Head of Performance and Delivery presented a report providing an updated position with regards to the risks identified and assessed on the Council’s Corporate Risk Register.

 

27 risks were currently present on the Corporate Risk Register and have been identified as those that have the potential to disrupt the Council’s strategic objectives and service delivery.

 

The report presents all relevant information and scoring of these risks, an overview being:

 

17 risks are currently rated as Significant (risk score 15-25)

7 risks are currently rated as High (risk score 8-12)

3 risk is currently rated as Moderate (risk score 4-6)

 

3 have increased in score

4 have decreased in score

20 have remained static

1 has been newly introduced

2 are proposed for closure

The following points were raised:

 

  • Councillor Hook asked a narrative could be included in the report.

 

  • Councillor Bernstein referred to CR.30 Staff Safety and stated that Member Safety should also be included as a risk.

 

It was stated that the S.151 Officer would pick this issue up with the relevant Executive Director.

 

It was also reported that the Member Development group were looking to update Member Safety Guidance to incorporate Operation Bridger and Operation Ford guidance.

 

  • Councillor Gartside referred to CR.9 Workforce Skills and Capability and asked how confident the Council was that the shortage of social workers would be addressed before May 2026.

 

The S.151 Officer reported that here were positive moves to recruit to permanent posts. He advised that he would seek an update from the Executive Director of Children and Young People.

 

  • Councillor Gartside referred to 63% rating significant and asked if this was a high number historically and whether there were targets to reduce to.

 

It was explained that the average for 2023/2024 was 65%. A suitable target would be considered.

 

  • Councillor Rubinstein referred to risks that weren’t included such as highways and potholes where accidents could happen and asked if there should be a risk in this area.

 

The S.151 Officer explained that there also departmental and service risk registers and stated that he would consult with the Director of Place to see which register these risks were included within.

 

  • David Webster stated that there was a typing error on page 33 – All risks have not been reviewed? Should this be all risks have been reviewed?

 

It was stated that yes, all risks had been reviewed.

 

  • David Webster referred to CR.11 H & S target score of 20 and asked if this should be lower and CR 23 having a target score of 12 but the score in the report at 10 and asked if this was the wrong way round.

 

It was explained that with regards to CR.11, Health and Safety have a sub group who report into the Health and Safety Group, two new staff have also been appointed within the team and actions were ongoing to reduce the score and target.

 

With regard to CR.23 it was reported that the CQC inspection had fed into the risk and  ...  view the full minutes text for item AU.111

AU.112

INTERNAL AUDIT DEVELOPMENT PLAN 2025 -2026 UPDATE pdf icon PDF 299 KB

Report from the Section 151 Officer attached

Additional documents:

Minutes:

The Section 151 Officer submitted a report outlining the work undertaken to implement the improvement actions identified from the Public Sector Internal Audit Standards (PSIAS) review which was presented to the Audit Committee on 8 April 2025. The improvements are contained within a development plan which outlines the action and the timescales for implementation.

 

The report and Appendix A enable Members to see the progress with implementation and to raise any questions on outstanding actions.

 

It was explained that following some changes within the team there were some areas of work that would be reallocated and that the GIAS self-assessment will also highlight any gaps where training might be required. This information will be updated at the April meeting.

 

  • Councillor Moss referred to his request for an update report of the Internal Audit Resource availability and asked when this information would be provided.

 

The S.151 Officer explained that due to changes within the staffing of the team the work had been delayed. A report would be brought  to the April meeting of the Committee.

 

Action 11 within the Development Plan requires the production of Audit Committee Terms of Reference which is attached for Members consideration.

 

Those present were given the opportunity to make comments and ask questions and the following points were raised:

 

  • Mr Webster referred to 65 of the Terms of Reference where it stated Council and Cabinet, he asked if this should just be Council. It was confirmed that this was the case.

 

  • Councillor Moss referred to the number of Members required for the Committee to be quorate as he felt that 3 members was a low number.

 

It was explained that every Council Committee had 3 as a quorum.

 

  • Councillor Moss referred to 29 where it stated ‘an officer’. He asked which officer?

 

It was explained that there were a number of officers from heads of service up to Executive Director.

 

  • Councillor Moss asked that this be changed to ‘most relevant’.

 

It was agreed:

 

That subject to the suggested amendments and following further input from the Monitoring Officer, the draft Terms of Reference be brought back to the next meeting of the Audit Committee before being submitted to Council for inclusion in the Council Constitution.

AU.113

INFORMATION GOVERNANCE UPDATE pdf icon PDF 631 KB

Report from Head of Performance and Delivery and Data Protection Officer attached

Minutes:

Head of Performance and Delivery and Data Protection Officer presented a report updating the Audit Committee on the Council’s Information Governance activity from 1 October 2024 to 30 September 2025. The report highlighted improvements in training compliance, performance at responding to requests for information and dealing with data breaches.

 

The report set out the number of Subject Access Requests (SAR) and SAR reviews received including open and overdue, Freedom of Information (FOI) requests including open and overdue and information in relation to data breaches.

 

The report also referred to the proposed procurement of case management software to increase capacity to respond to SAR requests and procure software to support FOI/EIR and SAR processes.

 

·         Councillor Moss noted that there had been an increase in figures since the previous year and asked if the process was costly.

 

It was confirmed that the numbers of FOIs and SARs received had increased in the past 12 months. It was also explained that the Council can refuse to respond if it would take 18 hours or more to produce and answer.

 

·         Councillor Hook asked whether there was a limit on the number of requests a person could submit.

 

It was explained that a person can submit unlimited requests.

 

The report also updated Members on GDPR training and no compliance.

 

Those present were given the opportunity to make comments and ask questions and the following pointes were raised:

 

·         Councillor Hayes referred to the proposed new software and stated that this would be a positive addition to the work of the team.

 

·         Councillor Hayes asked for clarification in relation to repeat request for information.

 

It was explained that if a number of requests were submitted in relation to a specific subject the information would be published on the council website so that it was accessible and the questioners would be directed to its location.

 

·         Councillor Berry referred to 20% of staff in one department not being compliant in GDPR training and stated that this figure seemed quite high.

 

It was explained that there were staff off on long term sick who may have lapsed and they would be included but it was also due to the fact that it was a rolling programme and therefore a snapshot in time. 

 

·         Councillor Moss asked whether agency staff were required to complete the training.

 

The Monitoring Officer confirmed that all agency staff were required to complete the training and new starters were required to complete as one of their first tasks. It was also reported that the Council were looking to ask new starters to have completed the training prior to starting their new roles.

 

It was agreed:

 

1.    That the contents of the report be noted.

 

2.    That an update report is presented to Audit Committee every 6 months.

 

AU.114

ANTI FRAUD & CORRUPTION STRATEGY 2025/2027 pdf icon PDF 379 KB

Report from the Section 151 officer attached

Additional documents:

Minutes:

The Section 151 Officer submitted a report providing an overview of the Anti-Fraud and Corruption Strategy, the Whistleblowing (Confidential Reporting) Policy, the Fraud & Corruption Prosecution Policy, Anti Bribery Policy and Anti Money Laundering Policy.

 

The Anti-Fraud & Corruption Strategy and associated polices, available on the internet, are dated 2023. This report brought to Audit Committee presents the Anti-Fraud & Corruption Strategy and the revised associated policies and seeks approval of these documents.

 

Those present were given the opportunity to ask questions and the following points were raised.

 

  • Councillor Hayes referred to reducing the risk of fraud through an education programme to staff and residents and asked how this would be done?

 

It was explained that residents have the opportunity to report fraud through the council website. It was also explained that by publicising successful cases that have led to prosecution will educate and encourage people to report.

 

  • Councillor Hook asked why the suppliers in schools had been removed from the anti-bribery policy.

 

It was explained that schools should have their own policies and strategies and this should be included within them. It was also explained that the majority of schools in Bury were now or soon would be academies.

 

  • Mr Webster referred to the whistleblowing and the employees suspicion of fraud where it stated what employees should do. He aske if a section on what employees shouldn’t do should be included to stop employees from carrying out their own investigations.

 

It was confirmed that this would be included and would state that it is not an exhaustive list.

 

  • Mr Webster referred to the newly introduced Economic Crime and Corporate Transparency Act and asked if this should be referenced.

 

It was confirmed that this would be included.

 

  • Councillor Moss referred to the Whistleblowing where it states that employees living in Bury could contact ‘their’ local Councillor. 

 

It was explained that this reference was being removed on the advice of the legal department.

 

·         Councillor Moss referred to the date on the Strategy as 2025 – 2027 and stated that the Strategy would not be implemented until 2026 so should be dated as 2026 – 2027.

 

It was stated that the date on the strategy would be removed.

 

It was also explained that reference on how to contact the Comptroller and Auditor General would be included and all references to Mazars would be changed to ‘Forvis Mazars’

 

It was agreed;

 

That subject to the amendments and additions highlighted in the comments,

 

  • The Audit Committee approve the Anti-Fraud & Corruption Strategy
  • The Audit Committee approve the Whistleblowing (Confidential Reporting) Policy
  • The Audit Committee approve the Fraud and Corruption Prosecution Policy
  • The Audit Committee approve the Anti Bribery Policy
  • The Audit Committee approve the Anti Money Laundering Policy

 

AU.115

EXCLUSION OF PRESS AND PUBLIC

To consider passing the appropriate resolution under Section 100(A)(4) of the Local Government Act 1972 that the press and public be excluded from the meeting during consideration of the following items of business since they involve the likely disclosure of the exempt information stated.

 

Minutes:

It was agreed:

 

That the press and public be excluded from the meeting under Section 100 (A)(4), Schedule 12(A) of the Local Government Act 1972, for the reason that the following business involves the disclosure of exempt information as detailed against the item

 

AU.116

COUNTER FRAUD TEAM MID YEAR REPORT 25/26

Report from the Section 151 officer is attached

Minutes:

A report from the S.151 Officer was presented to the Committee.

 

The report provided an update on the Annual Counter Fraud Plan 2025/26 and the work undertaken by the Counter Fraud Team during the period 1st April 2025 and 31st October 2025.

 

It was agreed:

 

That the contents of the report be noted.