Issue - decisions

Public Footpath 3 St Mary’s, Radcliffe – temporary closur

02/07/2020 - Public Footpath 3 St Mary’s, Radcliffe – temporary closur

Approval to the temporary closure under Section 14(1) of the Road Traffic Regulation Act 1984, of Public Footpath 3 St Marys, Radcliffe between York Street and Bury Road from Monday 06 July 2020 for a period of 6 months to enable ground remediation works and construction of an emergency access (anticipated duration of works is 3 months). The diversion route is via York St, Hardys Gate Bridge, Dumers Ln, part of footpath 104BUR, Whitefield Rd, Keswick Dr, Kendal Dr & Bury Rd & vice versa.